Creighton University,
Omaha, NE
Creighton University had Midwest Paving remove and
replace most all of their decorative streetscape. This
included removing existing concrete, installing new
concrete sidewalks, installing new decorative paver
bases and new decorative concrete stepping stones.
SEE DETAILS AND PHOTOS
Offutt Air Force Base,
Omaha, NE
Performed for the Omaha District Corps of Engineers,
this project included the removal and replacement of
existing concrete runway pavement. Sawcutting, chipping,
cleaning, placing grout and placing concrete were all a
part of this process (and all performed on the main
flightline). When we were complete, the Corps of
Engineers commented that we set a new standard for this
type of work. Also, after our contract was completed,
they called us back for some additional work and
actually had some of their inspectors watch us so they
could see the most effective way for this type of
patching to be accomplished.
SEE DETAILS AND PHOTOS
Cath Lab at VA
Medical Center, Omaha, NE
The VA Medical Center contracted with us to renovate
their existing Cath Lab and complete all prep work for
the installation of all new Cath Lab equipment. All new
mechanical and electrical systems, new walls, flooring
and finishes were included in our scope of work as well
as structural modifications to the existing floor deck
due to the increased weight of the new Phillips
equipment which was to be installed.
SEE DETAILS AND PHOTOS
Veterans Hospital 3rd
Floor Remodel - Grand Island, NE
This project was a 3.6 million dollar renovation to the
3rd Floor of the VA Hospital in Grand Island, NE. All
abatement, demo, new offices, electrical and HVAC
upgrades were included in the scope of work as well as
new nurses stations and finishes.
SEE DETAILS AND PHOTOS
Bureau of Reclamation
McCook Field Office Building Phase I
This project was the design and construction of a new
11,000 sq. ft. office building and all interior
finishes. The final contract amount was just over 1.8
million dollars and included the demolition of an
existing parking area, associated grading, footings and
foundations, wood frame construction, all electrical and
mechanical systems, poured concrete tornado shelter and
a separate emergency generator building. Our
relationship with the Bureau on this project lead to
their request that we stay on site and complete phase II
of this work which was the demolition of the old office
building and construction of new parking lot.
SEE
DETAILS AND PHOTOS
Bureau of Reclamation
McCook Field Office Phase II
This project started out as a $800,000 contact to abate
and tear down the old field office building and put in
an asphalt parking lot with associated site amenities
such as benches, sidewalks and tables. Through our value
engineering process we discovered that the closest
asphalt plant was 60 miles away and due to the high
trucking cost of the asphalt we could option to a 6"
concrete parking lot for close to the same dollar amount
as there was a concrete plant in town. The Bureau agreed
and we went with the concrete parking lot, doubling the
strength of their lot for a minimal cost increase . This
is a perfect example of how our value engineering
process helps our customers gain more value for their
dollar. SEE DETAILS AND PHOTOS
US Fish and Wildlife
Desoto Road Reconstruction
This project was a $1.2 million dollar phase I road
reconstruction project which consisted of asphalt
milling, grading, granular fill, culvert installation
and new hot mix asphalt overlay. The project was
completed on time and under budget and the US Fish and
Wildlife agency has just contracted with our firm for
phase II of this work. Phase II is similar in scope but
is twice as large, consists of multiple culverts and
includes a section of road which will be raised over 2'
in final design elevation.
SEE DETAILS AND PHOTOS
University of Nebraska
Medical Center
On this project we were subcontracted to Hawkins
Construction to provide all the site work and concrete
work on the remodel of the Medical Center. Colored
concrete and radius pieces were designed to highlight
the main entrance to the center.
SEE DETAILS AND PHOTOS
US Forest Service
Campground Rehabilitations - Lake George, CO.
Consisted of a new water treatment facility with new
HDPE waterline as well as new electrical service.
SEE
DETAILS AND PHOTOS
Halsey National
Forest, Nebraska
This project was new water service, new HDPE waterline
and a new treatment building.
SEE DETAILS AND PHOTOS
Palisades Horse
Campground, Pagosa Springs, Colorado
This project consisted of the removal of 600+ trees,
grading, crushed rock installation for roads and walks,
new water well, storage tank and HDPE waterline. Also
included in this project was a new solar power
electrical system as well as horse corrals, day use
pads, hydrants and fences.
SEE DETAILS AND PHOTOS
Offutt Air Force Base
Cemetery Rehabilitation
The work consisted of removing and resetting 635
headstones straight, level and plumb in a concrete
leveling pad on top of a continuous, reinforced concrete
trench footing. This project presented a number of
challenges as many of the headstones were broken below
grade, most all had been previously set in a mixture of
bricks, concrete, etc. which had to be removed and the
grade sloped dramatically from the North to South as
well as West to East. SEE DETAILS AND PHOTOS
Ramble Ridge Park
Rehabilitation
Ramble Ridge Park Rehabilitation was a complete
make-over for the park. The scope of work included
grading and installing over 3,000 lineal feet of 5’ wide
concrete trails, construction of a burnished block seat
wall and wood frame gazebo, construction of a wood frame
foot bridge over glue-lam structural members on concrete
piers and installation of a variety of plantings.
SEE
DETAILS AND PHOTOS
Fremont Nebraska Army
Reserve Center
This project involved not only construction but
engineering as well. Our task was to retrofit two
existing block buildings to meet new DOD Antiterrorism
criteria and provide and install a new state of the art
security system. Blast proof glass, steel reinforced
window frames, anchor type and size and structural
glazing were just a few of the considerations when
designing and providing the structural systems to meet
the static loads, shear force, tension force and
allowable member deformation requirements in the new
anti-terrorism criteria.
SEE DETAILS AND PHOTOS
|